Leased Line Installation Steps:

If you're considering a leased line for your business, here's an overview of the order steps and average lead times:

  1. KM1 - Order Acknowledged: 5 days
  2. KM2 - Order Placed with Supplier: 5 days
  3. KM3 - Order Verified and Accepted by Supplier: 13 days
  4. KM4 - Site Access Request (Survey): 14 days
  5. KM5 - No ECCs Confirmation / ECCs Confirmation (Excess Construction Costs
  6. KM6 - Estimated Delivery Date: 13 days
  7. KM7 - Site Access Request (On-site Works): 12 days
  8. KM8 - Site Access Request (Fit and Test): 16 days
  9. KM9 - Pre-Configured Router Shipment
  10. KM10 - Circuit Ready to Bring Live: 5 days
  11. KM11 - Service Handover: 5 days

Book a Discovery Call

LOOKING FOR A GAME-CHANGING TELECOMS SOLUTION?

Don't be shy. Get in touch with our helpful and friendly team below.

 

Messge Us

Call Us Free

reviews-your-coms
A seamless transition to Your Company Comms from our old provider, for much less, including new equipment and a customer service that is responsive, friendly and effective. Particular thanks to Lee and Jamie.
Dean Brothers
Company Director
YCG are delivering a true high level service around the clock and really know how to focus on client's needs, rather than offering what is popular on the market. I've been working with Rob for several years and very pleased of his professional account management levels. If your company feels its lacking personal care, you should definitely consider YCG as your service provider!
Robert Tornovsky
Company Director
Your Comms group make managing our SIM card estate easy by providing a single point of contact for all of our network providers. They're always quick to respond to queries, and ordering, cancelling and transferring lines is a painless process.
Ellen Swinburne
Company Director

Looking for more information about Landlines or Leased lines?

Speak to one of our experts today. Get the best price guaranteed.